2017年1月4日星期三

Concrete mixing plant manufacturers to teach you the operation process

Each machine is the order of the switch, if there is improper operation will form a lot of trouble. Concrete mixing station switching order are particularly important, if not properly, will form a concrete mixing station strike, the machine block. And so on, the formation of machine repair, conservation and protection. Today to us is how to operate the Concrete Mixing Plant.
Before starting to see a good range of concrete mixing station accessories, including butter, on the oil, at the same time before the boot to open the water switch to open the water pump and water - air compressor open storage silo door - open unloading belt - open Mixing the host - open the feed belt open ingredients (including aggregates, cement) - open water and so on, so start the concrete mixing plant before the operation to view the job.
Second, is the beginning of the Concrete Mixing Plant for the time of the switching sequence. (No material stored in the mixer) Unloading belt off (no material stored in the belt) Storage hopper door Closed air compressor (no material stored in the mixer) Cleaning agitator closed water valve switch off the total power.
So the order is extraordinarily important, if you do not operate properly, for example, you are stirring inside the host side of the mixing material, this time you shut down, the concrete will be blocked in the mixer inside the host.
http://www.zzxfjxwm.com/products/products.html

没有评论:

发表评论