Check the preparation of the screw conveyor

Screw conveyor for the concrete mixing station cement warehouse dedicated conveyor equipment, is also very important mixing station auxiliary equipment, although the screw conveyor is not used, but we can not ignore the protection of its work, it appears to us when the problem To a lot of trouble we know that if you do not want to let the cement in the transport problems, we need to do the following:
1. Before using the first need to check the need to add or replace the lubricant where the screw conveyor is small, but need to add a lot of lubricant, but a lot, so to check it;
2. Before use to clean up the machine to ensure that the entire machine clean;
3. Check the various fastening parts to see if loose, if loose, immediately tightened;
4. Check the spiral blade, screw shaft, sliding bearings and other parts prone to failure to ensure that these parts are intact; (pay special attention to check the spiral blade wear, spiral leaves more easily wear, if serious, then you need to change the new, To avoid the use of the process of failure.)
5. Check the screw conveyor reducer whether there is oil spill, and then see its clean up;
6. Before use in the air machine test run, in the test run to pay attention to the various parts to see if there are abnormal phenomena, or a strange sound. The following are the same as the.